Computer Room Raised Floor Installation Process

Jan 12, 2026

Leave a message

1. Clean the floor area where the raised floor will be installed, ensuring the surface is level and dry. The floor should already have a leveled cement mortar base, with height differences measured using a 2-meter level ruler being less than 4 mm.


2. Mark and position the support brackets on the cleaned floor.


3. Install the support brackets at the designated positions, install the frame, and adjust the height of the entire support structure.


4. Assemble the support beams, adjusting them to be level (a laser level is recommended), then tighten the screws to secure the beams.


5. Install the raised floor panels, trimming the edges as needed.


6. After the floor installation is complete, install the baseboards to protect and beautify the wall edges.


7. Clean the floor surface after construction is finished.

Send Inquiry